Still Short Of Funds For New Shelter Construction
Tweet |
The Construction of our new shelter in Hulu Langat is progressing well. This shelter can accommodate our 300+ dogs. We will strive to provide more regular updates on the progress. These pictures here were taken on the 17th August 2013.
Total construction is divided into 3 phases:-
Phase 1 – Office cum Clinic, 4 sick rooms, 11 individual kennels + 5 kennels (20ft x 30 ft)
Phase 1 – Office cum Clinic, 4 sick rooms, 11 individual kennels + 5 kennels (20ft x 30 ft)
Phase 2 – Kitchen, Isolation Cell, 5 Kennels (15ft x 20ft)
Phase 3 – workers room, store room , 4 kennels (20ft x 30ft)
Our 1-acre New Shelter’s work in progress updates in detail:-
As of 17th August 2013
As of 17th August 2013
Concrete floors for all 3 phases are completed
Brickwall is done for Phase 1 & 2, now work in progress for Phase 3
Roof beam – phase 1 is still in progress.
We still need 60k-80k to complete the whole construction works as well as to include water & electricity supply for our 300+ furkids. Target date of completion is October 2013. If you would like to help us achieve this mission by donating to us, kindly do so via our New Shelter fund account :- CIMB account No. 1428 0005 822051 under Treasurers’ names: Lim Mei Leng & Sim Hui Ling. Thank you in advance.
Also taking this opportunity to thank all who have helped with the construction fund to date. We couldn’t have gone this far without you!
Source: http://www.pawsmission.com/2013/08/still-short-of-funds-for-new-shelter.html